Capital Projects
 |
 |
How does a polarized plug work? What’s
the benefit of using it? |
 |
A
polarized plug is a plug with one large or wide
prong and one narrow one. It ensures that the
plug is inserted correctly in a socket and
reduces the risk of electrical
shock. | | |
 | |
Voltage Conversion Project
Groton Utilities continues its system upgrade projects. The 322
line, which is one of two lines that supply power to the
New London/Groton Naval Base is in the process of being
rebuilt. Also presently under construction are the rebuilding
of the 318 and 324 lines from Poquonnock River Substation
to Groton Long Point Substation. The 318/324-rebuild project
is scheduled to continue throughout the summer and be
completed in the fall of 2008. The 300 and 305, 35 kV
lines from Buddington Substation to Trails Corner Substation
have been rebuilt with the exception of the portion of
the lines that cross over Route #95. Engineering is waiting
on a permit from the State to complete that work.
The voltage conversion is continuing throughout Groton
Utilities territory. To date, the southern portion, or
43% of the territory, primary distribution voltage has
increased from 8.32 kV to 13.8 kV. As part of the Navy
Base Housing Project, the housing developments of Cherry
Circle, Dolphin Gardens, Nautilus Park North and Nautilus
Park South are complete. Construction is underway in the
final Navy Base Housing development Nautilus Park West.
The project consists of replacing the existing overhead
distribution lines with underground distribution facilities.
The preventive maintenance program continues with the
replacement of numerous aging poles. All of the protective
relays are tested by-annually, infrared testing of all
electrical facilities occur annually, and other critical
maintenance procedures are being accomplished on schedule.
Replacement of the traffic light controller and fixture
located at the intersection of Mitchell Street and Poquonnock
Road is schedule to start this spring. Once complete,
this will be the fourth out of seven traffic lights to
be upgraded. Capacitor banks were installed on the 35 kV primary distribution circuits at various locations to improve power factor levels and the efficiency of the distribution system. |